Well the safety audit has been carried out now and Mar City have tweaked the design but this I'm afraid has done little to allay concerns about safety. The key concern remains the proposed crossing which has poor visibility from the north side looking towards Dadlington.
Inexplicably the audit was not taken during morning on afternoon school start / end times and consequently reported "low vehicle flows / speeds (based upon the site visit)". Anybody who has visited at morning or evening rush hours knows this is anything but the case. Surely at least the safety auditors would have access to traffic flow information.
Some safety issues were identified in the report and in response Mar City are proposing the following modifications to the design:
1) There are now 'build outs'/ deflections incorporated into the 
roundabout. (this is just white paint on the road surface)
2) The roundabout is domed, to force deflection around the 
roundabout, which slows vehicles.
3) There is now a 'build out'/ tightened 
junction on the exit from the development, which will slow traffic exiting the 
site.(again this is just painted)
4) Beige anti-skid surfaces have been incorporated into the 
approaches.
5) Thermoplastic rumble strips have been incorporated, on the 
antiskid surface, approaching from Dadlington (this was not called for in the report)
The school have written to Highways expressing their ongoing concerns.